Prototype Home: Mt. Holly Construction Progress

Construction is underway on a fully funded single tiny-home prototype in Mt. Holly, New Jersey, with completion targeted for November 2026. The target remains subject to construction conditions and is separate from any Westampton village schedule. The prototype’s funding is separate from the proposed Westampton village. This prototype is not the full Pathway Village site; it is a practical construction test case that will help the project team evaluate design decisions, material choices, construction sequencing, cost assumptions, and lessons that can inform the proposed community. The latest photo update, shared September 28, 2026, shows window installation underway. The slideshow below also preserves earlier views of the enclosed shell, interior framing, and initial construction stages.

Why the prototype matters

The Mt. Holly prototype moves the project from concept toward construction-informed planning. A single built unit gives the team a way to test real-world construction methods, wall assembly, floor platform design, material handling, equipment access, sequencing, and the practical steps required before the model is scaled into a larger supportive village.

Lessons from this build will help refine Pathway Village planning, including unit design, construction methods, budgeting, site coordination, maintenance expectations, and the practical steps required to move from concept to implementation.

What the prototype is testing

  • Wall panel placement and assembly
  • Floor platform and footprint
  • Window and door openings
  • Construction sequencing
  • Material handling and staging
  • Build efficiency and repeatability
  • Equipment access and worker safety
  • Durability and maintenance implications
  • Budget and schedule assumptions
  • Lessons for future Pathway Village homes

Construction progress slideshow

The latest photo, shared September 28, 2026, shows windows going into the Filbert Street prototype. Browse all 17 photos, from the latest update back to the first wall assemblies.

Swipe or scroll sideways, use the Previous and Next links, or focus the gallery and use your keyboard’s arrow keys. Select a photo to view it full size.

Workers installing windows in the house-wrapped tiny-home prototype, with its covered front porch and exposed roof framing.
Shared September 28, 2026 · Window installationWindow installation is underway on the Filbert Street prototype. The exterior is wrapped, several windows are in place, and work continues around the openings.
1 / 17Next →
Exterior view of the Mt. Holly prototype with wall and roof sheathing installed and door and window openings framed.
Late July 2026 · Enclosed shell and interior framingExterior wall and roof sheathing define the prototype shell while the framed openings and elevated foundation remain visible.
Full-length interior view of the Mt. Holly prototype with roof sheathing, center supports, wall sheathing, and framed windows.
Late July 2026 · Enclosed shell and interior framingA full-length interior view records the roof structure, center support line, wall sheathing, and daylight through framed openings.
Interior view across the Mt. Holly prototype showing the roof structure, center supports, open floor area, and framed windows and doorway.
Late July 2026 · Enclosed shell and interior framingThe opposite interior perspective shows the open floor area, structural supports, and framed windows and doorway before interior build-out.
Wide view of the Pathway Village prototype with wall panels installed, a worker on the platform, and roof or floor panels staged for assembly.
July 2026 · Wall and roof assemblyWall panels are in place while roof and floor components are staged for the next phase of assembly.
Front exterior view of the Mt. Holly prototype showing raised wall panels, door and window openings, and the elevated platform foundation.
July 2026 · Wall and roof assemblyThe front elevation is framed, with door and window openings established and the raised platform clearly visible.
Interior view of the Pathway Village prototype showing wall openings, scaffolding, and roof panels being installed over the central space.
July 2026 · Wall and roof assemblyRoof panels are being set above the central interior space as the prototype moves toward enclosure.
Front view of the Mt. Holly prototype with framed entry and window openings, wall sheathing, and the raised deck platform.
July 2026 · Wall and roof assemblyThe main entry elevation now shows the home’s front doorway, window placement, and completed wall sheathing.
Side exterior view of the Mt. Holly prototype showing the long wall with window openings, the elevated platform, and foundation supports.
July 2026 · Wall and roof assemblyThe side wall is fully sheathed, with window openings and the elevated foundation system visible.
Interior view of the Pathway Village prototype showing framed wall openings, scaffolding, stacked panels, and roof framing in progress.
July 2026 · Wall and roof assemblyInterior framing, scaffolding, and staged panels show the prototype advancing through wall and roof assembly.
Wide exterior view of the Mt. Holly prototype during continued wall and roof assembly in July 2026.
July 2026 · Wall and roof assemblyA wide exterior view documents continued wall and roof assembly as the Mt. Holly prototype moves closer to full enclosure.
Closer vertical view of roof assembly and enclosure work on the Mt. Holly prototype in July 2026.
July 2026 · Wall and roof assemblyA closer view records roof assembly and enclosure work continuing on the Mt. Holly prototype.
Wall panels being raised on the Mt. Holly prototype tiny home
Early construction · Platform and wall assemblyWall panels are raised on the Mt. Holly prototype tiny home. This early construction stage helps the Pathway Village team evaluate panel placement, wall height, structural sequencing, and the practical steps required to move from platform framing to an enclosed unit.
Fastening and alignment work at the wall base of the Mt. Holly prototype tiny home
Early construction · Platform and wall assemblyFastening and alignment work during prototype construction. Close-up construction details like fastening, leveling, and panel connection help inform the durability, build process, and repeatability of future Pathway Village homes.
Builder on a ladder securing an upper wall section on the Mt. Holly prototype tiny home
Early construction · Platform and wall assemblyA builder secures an upper wall section on the prototype unit. The Mt. Holly build gives the project team a real-world test of wall assembly, window openings, equipment access, and safe construction practices before scaling to a larger village model.
Open floor platform and first wall sections of the Mt. Holly prototype tiny home
Early construction · Platform and wall assemblyPrototype floor platform and first wall sections in place. The open platform shows the footprint of the home and allows the team to evaluate layout, construction staging, material handling, and how individual units may be efficiently assembled.
Mt. Holly prototype tiny home beginning to take shape with platform and wall sections installed
Early construction · Platform and wall assemblyThe prototype begins to take shape on site in Mt. Holly. With the floor system and early wall sections installed, the project is moving from concept drawings to a physical model that can inform Pathway Village design, cost, and construction planning.

Lessons for Pathway Village

The prototype is intended to reduce risk before larger-scale implementation. It can help the project team refine construction assumptions, determine which methods are repeatable, improve cost estimates, identify maintenance considerations, and explain the project more clearly to funders, public officials, neighbors, and service partners.

What comes next

As additional construction photos become available, this page can be updated by date and stage: platform, wall assembly, roof or enclosure, windows and doors, utilities and rough-ins, interior finishes, exterior completion, and final lessons learned.