Affordable Homes Group

Pathway Village

15-Unit Development Budget

This page summarizes the current development budget for a 15-unit Pathway Village supportive tiny-home community. The budget should be used with the operating pro forma: this page addresses capital development costs, while the operating pro forma addresses ongoing annual operating costs.

Budget summary

The current 15-unit development budget shows a total project cost of $3,569,175, or $237,945 per unit. Direct unit construction is budgeted at $2,400,000, based on 15 homes at $160,000 each. The total reflects the all-in project cost, including acquisition, development costs, working capital, and project reserves.

Budget measureTotalPer unit @ 15
Acquisition – land and structures$250,000$16,667
Direct unit construction$2,400,000$160,000
Total soft costs$373,500$24,900
Total development costs$3,224,175$214,945
Total working capital$50,000$3,333
Total project reserves$45,000$3,000
Total project costs$3,569,175$237,945

What is included

The development budget includes land and structures, professional predevelopment services, design and engineering, construction management, legal and approval costs, audit and insurance costs, interim interest, closing and recording costs, direct construction, contingencies, developer fee, start-up working capital, and operating and replacement reserves.

Line itemTotalPer unit @ 15
Land$200,000$13,333
Structures$50,000$3,333
Total acquisition$250,000$16,667
Architecture fees$100,000$6,667
Engineering fees / site plan$25,000$1,667
Construction manager fee$150,000$10,000
Cost certification audit$20,000$1,333
Insurances$20,000$1,333
Interim interest$20,000$1,333
Total construction: 15 at $160,000 each$2,400,000$160,000
Hard cost contingency: 8%$192,000$12,800
Soft cost contingency: 0.5%$18,675$1,245
Developer fee$240,000$16,000
Working capital$50,000$3,333
Project reserves$45,000$3,000

Nonprofit budget note

Pathway Village is a nonprofit housing and supportive-services initiative. In this nonprofit context, the developer fee is a project budget line used to support development administration, coordination, compliance, financing, and implementation costs. It is not presented as private profit distribution.

How to read the budget

The budget should be presented as an all-in development estimate for a 15-unit demonstration village, not merely a per-home construction estimate. The $160,000 direct construction figure reflects the unit construction assumption. The $237,945 per-unit project cost reflects the broader development budget, including acquisition, professional services, contingencies, working capital, and reserves.

Why this matters for funders

The budget gives funders and public partners a clear capital target: approximately $3.57 million for the 15-unit demonstration project. It also helps distinguish capital needs from operating support. Capital funding builds the homes and site; operating funding supports staffing, services, maintenance, insurance, utilities, transportation, and accountability after occupancy begins.

Related materials

Review this page together with the operating pro forma, cost comparison, project brief, nonprofit governance and board page, project readiness summary, and funder/public partner FAQ.